Hereford 132Kv Compund

CES installed new control kiosks, new 66Kv and 132Kv Circuit breakers, new aluminium bar work.

WE installed & connected new panels in the 132Kv switch room, along with the installation of small power and lighting, including containment (ladder racking, tray & basket).

CES Ltd installed a new 50mm x 4mm earth mat and all new structures for cable sealing ends in addition to upgrading the existing earth mat with new 95mm tri-rated high frequency earthing.

We also installed additional multicore SWA wiring for controls from the 66Kv switch room to the 66Kv Compound.

The busbar was also upgraded to aluminium from the original copper.